OPAL: Commissioning a New Research Reactor
A Irwin 1), N de Lorenzo 2)
1) ANSTO, Lucas Heights, NSW, Australia
2) INVAP, Bariloche, Rio Negro, Argentina

Abstract:
On the 12 August 2006, the new OPAL research reactor was taken critical for the first time and full power 20 MW was achieved in November of the same year. This paper describes the issues encountered during the commissioning stages and also reviews the organisation and staffing during this period.